Yocto v1.0 Release Criteria

Release Criteria
Release Criteria Target Status
Functional Completion All M1, M2, M3 functional features implemented by EO M3

Current Criteria: Functional features are ready to go into master.

see Yocto 1.0 Schedule#Stabilization Phase Features and Activities
Build and Release

(Yocto)

Yocto 1.0 code builds reliably

Current criteria: All features in master can be built.

on-track to have stable builds by the end of Master Stabilization phase
Build and Release

(BSPs)

Yocto BSPs build reliably

Current criteria: Plan in place to build/QA BSPs by EO Feb.

Meeting Thursday to determine plan. Next Wednesday, the BSP build server will be off-line for a move, which may impact dates.
Open Bugs All bugs dispositioned; Show-stoppers fixed

Current criteria: All bugs have been dispositioned.

23 bugs have not been dispositioned (still in "New" state); Owners: Tom, Saul, Richard, Julie, Paul, Mark, Ke, Jeff, Edwin
Functional Tests 100% of planned tests executed and all bugs are logged in bugzilla

Current criteria: Weekly testing is performed on master and all bugs in bugzilla

testing starts in Feb
BSP Testing 100% of planned BSP tests executed

Current criteria: TBD - pending BSP plan

Alpha Feedback Alpha feedback included

Current criteria: Alpha begins Feb 11th

testing has begun; at least two bugs filed so far
Documentation Release documentation created and published

Current criteria: M4 schedule items completed

on-track
Build Performance Build takes 90 minutes (stretch goal = one hour) to do a complete rebuild of local sources of poky-image-sato on a developer's desktop. (The one we are using is: Intel(R) Core(TM) i7 CPU 940 @ 2.93GHz, 8 siblings, 4 cpu cores, total mem 6118644k, with: MACHINE=qemux86, BB_NUMBER_THREADS = "8", PARALLEL_MAKE = "-j 6", and only rpm packaging.)

Current criteria: Team has begun tracking these metrics per build and has defined plan to do engineering work to address.

investigating who can do this rebuild testing regularly
Marketing requirements complete Engineering requirements to the marketing plan are complete

Current criteria: Engineering requirements to the marketing plan are known.

need details on requirements
Publication Release and documentation are published on yoctoproject.org

Current criteria: None for this stage

Tunnel Creek BSP Release Criteria

Release Criteria
Release Criteria Target Status
Development progress Features implemented; Code completed Coding completed
Build and Release EMGD and non-EMGD BSPs build reliably Still building image with removable media fix.
Open Bugs All bugs dispositioned; Show-stoppers fixed TBD based on testing of latest build
Functional Tests 100% of planned tests executed Tom and Jaijun will test when final build is available.
Legal Compliance All legal requirements met Plan in place to create click-through. Getting host set up.
Documentation Release Notes created and published
Performance Performance targets achieved This will be done out of cycle.
Publication Release and documentation are published on yoctoproject.org on-track

Laverne Point Release Criteria

Release Criteria
Release Criteria Target Status
Development Progress Coding complete Coding completed
Build and Release Code builds reliably Release candidate is built.
Open Bugs All bugs dispositioned; Show-stoppers fixed No opens are show-stoppers. Open issues will be ID'd in release notes.
Functional Tests 100% of planned tests executed testing completed
Legal Compliance All legal requirements met tools run; requirements met
Performance Performance targets achieved N/A
Publication Release and documentation are published on yoctoproject.org Complete