Yocto v1.0 Release Criteria
Release Criteria Target Status
Development Progress All M1, M2, M3 features implemented by EO M3 on-track
Build and Release Yocto 1.0 and BSP code builds reliably on-track for Yocto 1.0, BSP build process TBD (not a target for 1.0?)
Open Bugs All bugs dispositioned; Show-stoppers fixed in progress
Functional Tests 100% of planned tests executed testing starts in Feb
BSP Testing 100% of planned BSP tests executed testing starts in Feb
Legal Compliance All legal requirements met in progress
Alpha Feedback Alpha feedback included testing starts 4/7
Documentation Release Notes created and published not yet
Performance Performance targets achieved TBD - discussion on reflector
Publication Release and documentation are published on yoctoproject.org on-track


Laverne Point Release Release Criteria
Release Criteria Target Status
Development Progress Coding complete Coding completed
Build and Release Code builds reliably Release candidate is built.
Open Bugs All bugs dispositioned; Show-stoppers fixed Any opens show-stoppers?
Functional Tests 100% of planned tests executed testing completed - if no show-stoppers, testing done
Legal Compliance All legal requirements met N/A?
Performance Performance targets achieved N/A?
Publication Release and documentation are published on yoctoproject.org on-track


Tunnel Creek BSP Release Release Criteria
Release Criteria Target Status
Development progress Features implemented; Code completed Coding completed
Build and Release EMGD and non-EMGD BSPs build reliably Problems building the no-EMGD image.
Open Bugs All bugs dispositioned; Show-stoppers fixed N/A until build exists.
Functional Tests 100% of planned tests executed EMGD tested, no-EMGD not  ??
Legal Compliance All legal requirements met need to create click-through agreement and get stakeholder buy-off
Documentation Release Notes created and published notes created; Scott is reviewing
Performance Performance targets achieved This will be done out of cycle.
Publication Release and documentation are published on yoctoproject.org on-track