Meta-intel-2.0-dizzy-1.7 release planning
From Yocto Project
Jump to navigationJump to search
For reference here is the Yocto Project 1.7 release schedule
- YP 1.7 M4 RC2 Build/QA test : Oct 8 – Oct 14
- YP 1.7 M4 RC3 Build/QA test : Oct 15 – Oct 21
- YP 1.7 M4 RC4 Build/QA test : Oct 22 – Oct 28
- YP 1.7 Release Final Publish : Oct 29 – Oct 31
Meta-intel 2.0 release schedule
- Meta-intel-2.0-dizzy-1.7 RC2 Build/QA test: Oct 8 – Oct 14
- Meta-intel-2.0-dizzy-1.7 RC3 Build/QA test: Oct 15 – Oct 21
- Meta-intel-2.0-dizzy-1.7 RC4 Build/QA test: Oct 22 – Oct 28
- Meta-intel-2.0-dizzy-1.7 RC5 Build/QA test: Oct 29 – Nov 4
- Meta-intel-2.0-dizzy-1.7 Release : Nov 5 – Nov 11
Remaining tasks for the meta-intel release
- Release branch and tags for QA use - Darren/Tom
- Per RC meta-intel build and QA test - Alex & IoTG team
- Kernel srcrev updates for all the BSPs - Bruce, Nitin & IoTG team
- Microcode commits - Nitin
- Machine setup tool commits - Nitin
- Follow the release process. Includes making BSP tar balls, Publishing of the BSPs, YP compatible certification, Release Notes - Michael + other
- Important bugs to fix before the release:
- bug #6162 - Bruce
For reference: Yocto Release Engineering