Introduction

This article is the test plan for Toaster.

Objectives

The test process focuses on:

  • validating the data collected from the build process
  • verifying the correct functioning of the Toaster GUI.

Test Areas

Toaster consists of two big components, as follows:

1. Backend

Functionality tests

  • REST API verification – create Django tests to detect API calls returning no data;
  • Calculation of the data collection rate;
  • Verify if all the links from the simple UI are available;
  • Verify the quality of the data collected through the simple UI;

Usability tests

2. Frontend

Functionality tests

  • Manual testing in the first stage;
  • Automate testing using Selenium, in the second stage;

Compatibility tests

  • Verify the behavior of the GUI on different browsers and operating systems;

Usability tests

Performance tests

  • Stress testing (e.g. display appropriate error messages when the system is under stress);