Web Hob design project with T&T
From Yocto Project
				
				
				Jump to navigationJump to search
				
				
This page contains information on the Web Hob project to develop a web-based UI for the Yocto project.
Mailing List: https://lists.yoctoproject.org/listinfo/webhob
Design
Latest Files
- File:Prototype-Stage 2-File Browsing & Visualisation-INT-002-0.15.pdf — FIle browsing & build analysis prototype for Stage II (bright blue links, buttons, etc. are clickable)
 - File:User Test 1 Findings-INT-002.pdf — Summary of feedback gathered on the Stage I designs
 - File:Wireframes-Stage 1-INT-002-0.10.pdf — Final Stage I Wireframes (bright blue links, buttons, etc. are clickable)
 - File:Web Hob content structure.pdf — An outline of the structure of the Web Hob application
 
Prototype Index
| Sprint | Version | Stage | Scope | Link | 
|---|---|---|---|---|
| 1 | 1 | I,III | Build analysis | prototype | 
| 2 | 1 | II,III | Projects and builds | prototype | 
| 2 | 2 | II,III | Projects and builds | prototype | 
| 2 | 3 | II,III | Projects and builds | prototype | 
| 2 | 1 | II,III | File browsing and multi-user | prototype | 
| 2 | 2 | I,II,III | File browsing and build analysis | prototype | 
| 2 | 4 | I,II,III | All scenarios | prototype | 
| 2 | 5 | I,II,III | All scenarios | prototype | 
- Sprint is the design sprint (or phase) during which the prototype was produced. There are 2 design sprints in this project.
 
- Version indicates how many iterations of each prototype we created as part of the design process
 
- Stage refers to the Web Hob stages identified by Tobias & Tobias and outlined further down this page
 
- Scope indicates, at a high level, which scenarios are addressed by the prototype
 
- Link to the Yocto Project git repository where the prototype is hosted
 
Stage II & III
Scenarios Covered
- Create Build 
- Set up Project
 - Choose Hardware
 - Set Preferences
 - Specify Layer(s)
 - Specify base image and package(s)
 - Run Build
 
 - Install Web Hob Server
- Configure team servers
 - Select team options and configure
 
 - Error Messaging 
- View error logs
 
 - Refine scenarios from Stage I
 
Schedule
- 4 Feb 2013 — Workshop
 - 8 Feb — 1st review
 - 12–14 Feb — User testing
 - 15 Feb — User testing review
 - 20 Feb — 2nd review
 - 22 Feb — Final review
 
Stage I
Scenarios Covered
- Show Build Metrics (minimal)
- Identify image (minimal)
 - Define scope of analysis (minimal)
 - Run analysis of image (minimal)
 - View analysis overview (minimal)
 
 - Finding/Viewing Builds (minimal)
- View list of projects/builds (minimal)
 
 - Install Single-User Web Hob (minimal)
- Check prerequisites (minimal)
 - Download/git clone Web Hob (minimal)
 - Install single-user option (minimal)
 
 
Schedule
- 11 Jan 2013 — Kickoff
 - 14 Jan — Workshop
 - 18 Jan — 1st review
 - 22–24 Jan — User testing
 - 25 Jan — User testing review
 - 30 Jan — 2nd review
 - 1 Feb — Final review
 
Old Files
Previous Versions
- Prototype 1.0
 - WebHob Design — Archived - Design and documentation for the first Web Hob project, now superseded by the above.
 - Web UI 0.1: File:HOB WEB architecture overview v0 1.pdf (deprecated)