Web Hob design project with T&T
From Yocto Project
Jump to navigationJump to search
This page contains information on the Web Hob project to develop a web-based UI for the Yocto project.
Mailing List: https://lists.yoctoproject.org/listinfo/webhob
Design
Latest Files
- File:User Test 2 Findings-INT-002.pdf — Summary of feedback gathered on the Stage II designs
- File:Web Hob content structure.pdf — An outline of the structure of the Web Hob application
- File:User Test 1 Findings-INT-002.pdf — Summary of feedback gathered on the Stage I designs
- File:Wireframes-Stage 1-INT-002-0.10.pdf — Final Stage I Wireframes (bright blue links, buttons, etc. are clickable)
- File:User Test 2 Findings-INT-002.pdf - Summary of feedback gathered on Stage II designs
Prototype Index
Sprint | Version | Stage | Scope | Link |
---|---|---|---|---|
1 | 1 | I,III | Build analysis | prototype |
2 | 1 | II,III | Projects and builds | prototype |
2 | 2 | II,III | Projects and builds | prototype |
2 | 3 | II,III | Projects and builds | prototype |
2 | 1 | II,III | File browsing and multi-user | prototype |
2 | 2 | I,II,III | File browsing and build analysis | prototype |
2 | 4 | I,II,III | All scenarios | prototype |
2 | 5 | I,II,III | All scenarios | prototype |
- Sprint is the design sprint (or phase) during which the prototype was produced. There are 2 design sprints in this project.
- Version indicates how many iterations of each prototype we created as part of the design process
- Stage refers to the Web Hob stages identified by Tobias & Tobias and outlined further down this page
- Scope indicates, at a high level, which scenarios are addressed by the prototype
- Link to the Yocto Project git repository where the prototype is hosted
Stage II & III
Scenarios Covered
- Create Build
- Set up Project
- Choose Hardware
- Set Preferences
- Specify Layer(s)
- Specify base image and package(s)
- Run Build
- Install Web Hob Server
- Configure team servers
- Select team options and configure
- Error Messaging
- View error logs
- Refine scenarios from Stage I
Schedule
- 4 Feb 2013 — Workshop
- 8 Feb — 1st review
- 12–14 Feb — User testing
- 15 Feb — User testing review
- 20 Feb — 2nd review
- 22 Feb — Final review
Stage I
Scenarios Covered
- Show Build Metrics (minimal)
- Identify image (minimal)
- Define scope of analysis (minimal)
- Run analysis of image (minimal)
- View analysis overview (minimal)
- Finding/Viewing Builds (minimal)
- View list of projects/builds (minimal)
- Install Single-User Web Hob (minimal)
- Check prerequisites (minimal)
- Download/git clone Web Hob (minimal)
- Install single-user option (minimal)
Schedule
- 11 Jan 2013 — Kickoff
- 14 Jan — Workshop
- 18 Jan — 1st review
- 22–24 Jan — User testing
- 25 Jan — User testing review
- 30 Jan — 2nd review
- 1 Feb — Final review
Old Files
- File:Prototype-Stage 2-File Browsing & Visualisation-INT-002-0.15.pdf — FIle browsing & build analysis prototype for Stage II (bright blue links, buttons, etc. are clickable)
- File:Wireframes-Stage 1-INT-002-0.6.pdf
- Prototype 0.2
Previous Versions
- Prototype 1.0
- WebHob Design — Archived - Design and documentation for the first Web Hob project, now superseded by the above.
- Web UI 0.1: File:HOB WEB architecture overview v0 1.pdf (deprecated)