Yocto Project v1.0 Release Criteria

From Yocto Project
Revision as of 17:10, 1 March 2011 by Jnfleisc (talk | contribs) (added results from 3/1 Release Tracking meeting)
Jump to navigationJump to search

Yocto v1.0 Release Criteria

Release Criteria
Release Criteria Target Status
Functional Completion All M1, M2, M3 functional features implemented by EO M3

M4 (Gold) Criteria: All features and BSPs are in build.

see Yocto 1.0 Schedule#Stabilization Phase Features and Activities

Richard will send a note regarding the four open features.

Build and Release

(Yocto)

Yocto 1.0 code builds reliably

M4 (Gold) criteria: All features in master can be built with no errors.

On track for builds by Friday. Working on corner cases with respect to being branch aware.
Build and Release

(BSPs)

Yocto BSPs build reliably

M4 (Gold) criteria: BSPs can be build from master with no errors.

Could build at least one BSP. On-track for Friday. Beagleboard issue (Beagleboard failed doing runstrip on uboot during do_populate_sysroot) may be fixed - investigating.
Open Bugs All bugs dispositioned; Show-stoppers fixed

M4 (Gold) criteria: All bugs have been dispositioned. Critical/High bugs targeted for M4 have been fixed.

Total new defects: 11 (Bruce, Ke, Dongxiao, Liping, Nitin, Qing)

74 total open defects targeted for 1.0 Critical: 0 High: 16 Medium: 53 Low: 5

Functional Tests 100% of planned tests executed and all bugs are logged in bugzilla

M4 (Gold) criteria: All planned tests are executed and results are logged in bugzilla

QA is running tests this week.
BSP Testing 100% of planned BSP tests executed

M4 (Gold) criteria: All planned BSP tests are executed

Team is currently blocked, but plan to be able to test next week.
Alpha Feedback Alpha feedback included

M4 (Gold) criteria: Alpha begins Feb 11th and completes Feb 23rd

Program completed. Saul is parsing final results.
Documentation Release documentation created and published

M4 (Gold) criteria: M4 schedule items completed

Yocto_1.0_Schedule#Documentation_Deliverables
Build Performance Build takes 90 minutes (stretch goal = one hour) to do a complete rebuild of local sources of poky-image-sato on a developer's desktop. (The one we are using is: Intel(R) Core(TM) i7 CPU 940 @ 2.93GHz, 8 siblings, 4 cpu cores, total mem 6118644k, with: MACHINE=qemux86, BB_NUMBER_THREADS = "8", PARALLEL_MAKE = "-j 6", and only rpm packaging.)

M4 (Gold) criteria: Goal above is reached.

Team moved down from 109 minute builds to 107 due to some tweaks Richard made. Next steps: Richard, Dongxiao analyze and make changes. Richard review notes from Dave's performance contact. Dongxiao review notes from Dave's performance contact in PRC.
ADT User Workshop ADT User Workshop is held where developers use ADT tools to demo software

M4 (Gold) criteria: Workshop is complete.

Running into problems recruiting people.
Marketing requirements complete Engineering requirements to the marketing plan are complete

M4 (Gold) criteria: Yocto demo is prepared for ELC.

Demo schedule:

March 4th – 0.9 demo brought up against 1.0 branch on eMenlow, Netbook, Router Station Pro (Joshua) - on-track March 11th – Know which media codecs we need/which videos we need to support (Julie) March 18th – Required software for video brought up March 18th – PPC, Beagleboard done March 18th – Sandybridge received or no-go for Sandybridge  This could be a “when we get it” test milestone. March 25th – Images built and tested for each target / Demo app brought up March 25th – Sandybridge development done March 25th – Demo integrated without Sandybridge April 1st – Demo integrated and ready for Linux Collab Summit April 5th – Marketing trained on demo

Publication Release and documentation are published on yoctoproject.org

M4 (Gold) criteria: Yocto Project 1.0 published and announced

Tunnel Creek BSP Release Criteria

Release Criteria
Release Criteria Target Status
Development progress Features implemented; Code completed Coding completed
Build and Release EMGD and non-EMGD BSPs build reliably Build completed
Open Bugs All bugs dispositioned; Show-stoppers fixed Only minor bugs found (724, 725)
Functional Tests 100% of planned tests executed Tom tested. Jiajun will test Thursday.
Legal Compliance All legal requirements met Account is set up for click-through. Click-through team has info they need.
Documentation Release Notes created and published Scott/Tom are finalizing and things look good.
Performance Performance targets achieved This will be done out of cycle.
Publication Release and documentation are published on yoctoproject.org on-track

Laverne Point Release Criteria

Release Criteria
Release Criteria Target Status
Development Progress Coding complete Coding completed
Build and Release Code builds reliably Release candidate is built.
Open Bugs All bugs dispositioned; Show-stoppers fixed No opens are show-stoppers. Open issues will be ID'd in release notes.
Functional Tests 100% of planned tests executed testing completed
Legal Compliance All legal requirements met tools run; requirements met
Performance Performance targets achieved N/A
Publication Release and documentation are published on yoctoproject.org Complete