Yocto Project v1.1 Release Criteria
From Yocto Project
Jump to navigationJump to search
The Release Criteria for the various Yocto Project 1.1 releases are below.
Yocto Project 1.1
Milestone 4
Release Criteria | Milestone 4 Target | Milestone 4 Status |
Functional Completion | A significant part of all the 1.1 Med+ bug fixes and BSPs are in the build. | see https://wiki.yoctoproject.org/wiki/Yocto_1.1_Schedule for details Remaining Med+ bugs: 1.1 remaining bugs (Med+) Fixed 186 bugs as of 10/17/2011 |
Build and Release (Yocto) | All M4 bug fixes can be built with no errors. | RC4 generated, full test complete, no show stoppers or major issues. |
Build and Release (BSPs) | Core and meta-intel BSPs can be built with no errors. | All BSPs build with no problem |
Open Bugs | All bugs have been dispositioned. High issues have been fixed. | [1] - 0 new bugs for 1.1. HIGH priority bugs - 0 high bugs for 1.1 See trend chart at https://wiki.yoctoproject.org/wiki/Yocto_Bug_Trend. |
Functional Tests | 100% of planned tests are executed and results are logged in bugzilla. | Complete https://wiki.yoctoproject.org/wiki/Yocto_1.1_Milestone_Test_Report |
Distros Tested | Fedora, Ubuntu, Opensuse (N+1) | Fedora 15, Ubuntu 11.04, Opensuse 11.4, Fedora 16 Alpha, Ubuntu 11.10 Alpha3, Opensuse 12.1 M3: Complete and all passed |
BSP Testing | 100% of planned tests are executed and results are logged in bugzilla. | Complete https://wiki.yoctoproject.org/wiki/Yocto_1.1_Milestone_Test_Report |
Documentation | All documents listed in M4 feature list | Doc pull request sent, complete |
Build Performance | None | N/A |
Upstream Commits | Have upstream status updated on 90% of patches (so that we can have a status update) | Complete |
Marketing Deliverables | None | N/A |
Publication | Yocto 1.1 release is announced |
Milestone 3
Release Criteria | Milestone 3 Target | Milestone 3 Status |
Functional Completion | All M3 features and BSPs are in the build. | see https://wiki.yoctoproject.org/wiki/Yocto_1.1_Schedule for details |
Build and Release (Yocto) | All M3 features can be built with no errors. | RC3 generated, build is good with minor issues |
Build and Release (BSPs) | Core and meta-intel BSPs can be built with no errors. | RC3 generated, build is good with minor issues |
Open Bugs | All bugs have been dispositioned. High issues have been fixed. | NEW bugs - 0 new bugs for M3. HIGH priority bugs - 1 high bugs for M3, already fixed See trend chart at https://wiki.yoctoproject.org/wiki/Yocto_Bug_Trend. |
Functional Tests | 100% of planned tests are executed and results are logged in bugzilla. | There are known problems, but we have fix in master. Bug trend is going to the right direction. WDD is down. https://wiki.yoctoproject.org/wiki/Yocto_1.1_Milestone_Test_Report |
Distros Tested | Fedora, Ubuntu, Opensuse | Fedora15 build failed, but fixed in master, Opensuse 11.4 and Ubuntu 11.04 pass. |
BSP Testing | 100% of planned tests are executed and results are logged in bugzilla. | We are good here. https://wiki.yoctoproject.org/wiki/Yocto_1.1_Milestone_Test_Report |
Documentation | None | |
Build Performance | RFC ready | RFC sent |
Upstream Commits | Have upstream status updated on 90% of patches (so that we can have a status update) | Target met |
Marketing Deliverables | None | |
Publication | M3 release is announced | Complete |
Milestone 2
Release Criteria | Milestone 2 Target | Milestone 2 Status |
Functional Completion | All M2 features and BSPs are in the build. | see https://wiki.yoctoproject.org/wiki/Yocto_1.1_Schedule for details |
Build and Release (Yocto) | All M2 features can be built with no errors. | M2 RC3 generated, pulled in as many features as possible |
Build and Release (BSPs) | Core and meta-intel BSPs can be built with no errors. | Target met |
Open Bugs | All bugs have been dispositioned. High issues have been fixed. | NEW bugs - No new bugs for M2. HIGH priority bugs - no high bugs for M2 See trend chart at https://wiki.yoctoproject.org/wiki/Yocto_Bug_Trend. |
Functional Tests | 100% of planned tests are executed and results are logged in bugzilla. | Target met. https://wiki.yoctoproject.org/wiki/Yocto_1.1_Milestone_Test_Report |
Distros Tested | Fedora, Ubuntu, Opensuse | Fedora15, Opensuse 11.4 and Ubuntu 11.04. |
BSP Testing | 100% of planned tests are executed and results are logged in bugzilla. | Target met. https://wiki.yoctoproject.org/wiki/Yocto_1.1_Milestone_Test_Report |
Documentation | A reviewable draft of the Yocto Project Development Guide. | On Track |
Build Performance | Improving build performance. | Some degradation due to many features integrated. Risk understood, has plan for improvement in M3 |
Upstream Commits | Have upstream status updated on 90% of patches (so that we can have a status update) | Status updated, target met. |
Marketing Deliverables | None | |
Publication | M2 release is announced | Announced to the public via yoctoproject.org mailing list |
Milestone 1
Release Criteria | Milestone 1 Target | Milestone 1 Status |
Functional Completion | All M1 features and BSPs are in the build. | All desired features are in build. One documentation publishing fix remains. see https://wiki.yoctoproject.org/wiki/Yocto_1.1_Schedule for details |
Build and Release (Yocto) | All M1 features can be built with no errors. | Build pulled in all fixes possible. |
Build and Release (BSPs) | Core and meta-intel BSPs can be built with no errors. | Build pulled in all fixes possible. |
Open Bugs | All bugs have been dispositioned. High issues have been fixed. | NEW bugs - 1 unaccepted New bugs for 1.1 M1. HIGH priority bugs - no HIGH priority bugs for 1.1 M1 See trend chart at https://wiki.yoctoproject.org/wiki/Yocto_Bug_Trend. |
Functional Tests | 100% of planned tests are executed and results are logged in bugzilla. | https://wiki.yoctoproject.org/wiki/Yocto_1.1_Milestone_Test_Report |
Distros Tested | Fedora, Ubuntu, Opensuse | Fedora 14, Ubuntu 11.04, Opensuse 11.4 |
BSP Testing | 100% of planned tests are executed and results are logged in bugzilla. | https://wiki.yoctoproject.org/wiki/Yocto_1.1_Milestone_Test_Report |
Documentation | M1 documentation deliverables are complete. | Only deliverable is allowing documentation to be updated even after code freeze. On-track. |
Build Performance | Plan for improving performance is defined. | Performance goals for M1 (mostly planning goals) were met. See schedule for details. Build is at 102 minutes. |
Upstream Commits | Have upstream status updated on 90% of patches (so that we can have a status update) | At 85%, which is good enough for alpha. |
Marketing Deliverables | Giveaway plans defined | At least one giveaway plan has been defined and is in the process of being implemented. |
Publication | M1 release is announced | Complete |