Yocto 1.1 Schedule: Difference between revisions
From Yocto Project
Jump to navigationJump to search
(initial version) |
(added new M2 items) |
||
Line 21: | Line 21: | ||
|- | |- | ||
|| 1.0 Carryover || Image Creator || finish the Image Creator to add features pushed out from 1.0 || 1 || Review || Josh + Jessica || 1.0 Carryover || | || 1.0 Carryover || Image Creator || finish the Image Creator to add features pushed out from 1.0 || 1 || Review || Josh + Jessica || 1.0 Carryover || | ||
|- | |||
|| Architecture || Layer Tooling || This includes the architectural work plus implementing the changes || 1 || Review || Richard || Architect || | |||
|- | |||
|| Meta-data || Upstream our patches || Placeholder for time for the team to upstream patches || 1 || Review || Saul || Meta-Data Team|| | |||
|} | |} | ||
Revision as of 20:17, 14 March 2011
October 2011 (release date: October 6, 2011)
The detailed milestone map for the October 2011 release of Yocto is as below.
pre-M1 (March 14 to April 18 -- Feature List and Schedule Defined April 18)
- Features Submitted to web - by April 1st
- Features prioritized and added to schedule - by April 18th
M1 (Apr 18 to Jun 13 -- Design Complete Apr 25, Dev Complete May 23, Stabilize Complete Jun 6, Release Complete Jun 13)
Group | Feature Name | Description | Priority | Status | Owner | Source | Comments / Bugzilla Links |
1.0 Carryover | multi-lib | multi-lib support for 32-bit & 64-bit and capable of being installed at the same time | 1 | Review | Richard | 1.0 Carryover |
M2 (May 30 to Jul 25 -- Design Complete Jun 6, Dev Complete Jul 4, Stabilize Complete Jul 18, Release Complete Jul 25)
Group | Feature Name | Description | Priority | Status | Owner | Source | Comments / Bugzilla Links |
1.0 Carryover | Image Creator | finish the Image Creator to add features pushed out from 1.0 | 1 | Review | Josh + Jessica | 1.0 Carryover | |
Architecture | Layer Tooling | This includes the architectural work plus implementing the changes | 1 | Review | Richard | Architect | |
Meta-data | Upstream our patches | Placeholder for time for the team to upstream patches | 1 | Review | Saul | Meta-Data Team |
M3 (Jul 11 to Aug 15 -- Design Complete Jul 18, Dev Complete Jul 25, Stabilize Complete Aug 8, Release Complete Aug 15)
Group | Feature Name | Description | Priority | Status | Owner | Source | Comments / Bugzilla Links |
X | X | X | 1 | Review | X | X |
M4 (Aug 15 to Oct 6 -- Stabilize Complete Aug 29, Release Complete Oct 3)
Group | Feature Name | Description | Priority | Status | Owner | Source | Comments / Bugzilla Links |
X | X | X | 1 | Review | X | X |