Yocto Project v1.1 Release Criteria: Difference between revisions
From Yocto Project
Jump to navigationJump to search
Line 2: | Line 2: | ||
= Yocto Project 1.1 = | = Yocto Project 1.1 = | ||
== Milestone 2 == | |||
{| border="1" {{table}} | |||
| ! scope="col" bgcolor="grey" | '''Release Criteria''' || ! scope="col" bgcolor="grey" | '''Milestone 2 Target''' || ! scope="col" bgcolor="grey" | '''Milestone 1 Status''' | |||
|- | |||
| Functional Completion || All M2 features and BSPs are in the build. || bgcolor="" | [[File:Schedule-status-M2.png]]<br><br>see https://wiki.yoctoproject.org/wiki/Yocto_1.1_Schedule for details | |||
|- | |||
| Build and Release (Yocto) || All M2 features can be built with no errors. || bgcolor="" | To be updated. | |||
|- Working | |||
| Build and Release (BSPs) || Core and meta-intel BSPs can be built with no errors. || bgcolor="" | to be updated. | |||
|- | |||
| Open Bugs || All bugs have been dispositioned. High issues have been fixed. || bgcolor="" | [http://bugzilla.yoctoproject.org/buglist.cgi?query_format=advanced&bug_status=NEW NEW bugs] - To be Updated.<br>[http://bugzilla.yoctoproject.org/buglist.cgi?bug_status=NEW&bug_status=ACCEPTED&bug_status=REOPENED&bug_status=NEEDINFO&bug_status=WaitForUpstream&columnlist=bug_severity%2Cpriority%2Ctarget_milestone%2Cop_sys%2Cassigned_to%2Cbug_status%2Cresolution%2Cshort_desc&priority=High&query_format=advanced&target_milestone=---&target_milestone=0.9%20M1&target_milestone=0.9%20M2&target_milestone=0.9%20M3&target_milestone=0.9%20M4&target_milestone=0.9.1&target_milestone=0.9.2&target_milestone=1.0%20M1&target_milestone=1.0%20M2&target_milestone=1.0%20M3&target_milestone=1.0%20M4&target_milestone=1.1&target_milestone=1.1%20M1&target_milestone=1.1%20M2&target_milestone=1.1%20M3&target_milestone=1.1%20M4&target_milestone=Q1&target_milestone=Q2&target_milestone=Q3&target_milestone=Q4&query_based_on= HIGH priority bugs] - to be updated <br>See trend chart at https://wiki.pokylinux.org/wiki/Yocto_Bug_Trend. | |||
|- | |||
| Functional Tests || 100% of planned tests are executed and results are logged in bugzilla. || bgcolor="" | https://wiki.pokylinux.org/wiki/Yocto_1.1_Milestone_Test_Report | |||
|- | |||
| Distros Tested || Fedora, Ubuntu, Opensuse (N+1) || bgcolor="" | to be updated | |||
|- | |||
| BSP Testing || 100% of planned tests are executed and results are logged in bugzilla. || bgcolor="" | https://wiki.pokylinux.org/wiki/Yocto_1.1_Milestone_Test_Report | |||
|- | |||
| Documentation || M2 documentation deliverables are complete. || bgcolor="" | to be updated. | |||
|- | |||
| Build Performance || Plan for improving performance is defined. || bgcolor="" | to be updated. | |||
|- | |||
| Upstream Commits || Have upstream status updated on 90% of patches (so that we can have a status update) || bgcolor="" | to be updated. | |||
|- | |||
| Marketing Deliverables || Giveaway plans defined || bgcolor="" | to be updated. | |||
|- | |||
| Publication || M2 release is announced || | |||
|} | |||
== Milestone 1 == | |||
{| border="1" {{table}} | {| border="1" {{table}} | ||
| ! scope="col" bgcolor="grey" | '''Release Criteria''' || ! scope="col" bgcolor="grey" | '''Milestone 1 Target''' || ! scope="col" bgcolor="grey" | '''Milestone 1 Status''' | | ! scope="col" bgcolor="grey" | '''Release Criteria''' || ! scope="col" bgcolor="grey" | '''Milestone 1 Target''' || ! scope="col" bgcolor="grey" | '''Milestone 1 Status''' |
Revision as of 19:08, 10 June 2011
The Release Criteria for the various Yocto Project 1.1 releases are below.
Yocto Project 1.1
Milestone 2
Release Criteria | Milestone 2 Target | Milestone 1 Status |
Functional Completion | All M2 features and BSPs are in the build. | see https://wiki.yoctoproject.org/wiki/Yocto_1.1_Schedule for details |
Build and Release (Yocto) | All M2 features can be built with no errors. | To be updated. |
Build and Release (BSPs) | Core and meta-intel BSPs can be built with no errors. | to be updated. |
Open Bugs | All bugs have been dispositioned. High issues have been fixed. | NEW bugs - To be Updated. HIGH priority bugs - to be updated See trend chart at https://wiki.pokylinux.org/wiki/Yocto_Bug_Trend. |
Functional Tests | 100% of planned tests are executed and results are logged in bugzilla. | https://wiki.pokylinux.org/wiki/Yocto_1.1_Milestone_Test_Report |
Distros Tested | Fedora, Ubuntu, Opensuse (N+1) | to be updated |
BSP Testing | 100% of planned tests are executed and results are logged in bugzilla. | https://wiki.pokylinux.org/wiki/Yocto_1.1_Milestone_Test_Report |
Documentation | M2 documentation deliverables are complete. | to be updated. |
Build Performance | Plan for improving performance is defined. | to be updated. |
Upstream Commits | Have upstream status updated on 90% of patches (so that we can have a status update) | to be updated. |
Marketing Deliverables | Giveaway plans defined | to be updated. |
Publication | M2 release is announced |
Milestone 1
Release Criteria | Milestone 1 Target | Milestone 1 Status |
Functional Completion | All M1 features and BSPs are in the build. | All desired features are in build. One documentation publishing fix remains. see https://wiki.yoctoproject.org/wiki/Yocto_1.1_Schedule for details |
Build and Release (Yocto) | All M1 features can be built with no errors. | Build pulled in all fixes possible. |
Build and Release (BSPs) | Core and meta-intel BSPs can be built with no errors. | Build pulled in all fixes possible. |
Open Bugs | All bugs have been dispositioned. High issues have been fixed. | NEW bugs - 1 unaccepted New bugs for 1.1 M1. HIGH priority bugs - no HIGH priority bugs for 1.1 M1 See trend chart at https://wiki.pokylinux.org/wiki/Yocto_Bug_Trend. |
Functional Tests | 100% of planned tests are executed and results are logged in bugzilla. | https://wiki.pokylinux.org/wiki/Yocto_1.1_Milestone_Test_Report |
Distros Tested | Fedora, Ubuntu, Opensuse | Fedora 14, Ubuntu 11.04, Opensuse 11.4 |
BSP Testing | 100% of planned tests are executed and results are logged in bugzilla. | https://wiki.pokylinux.org/wiki/Yocto_1.1_Milestone_Test_Report |
Documentation | M1 documentation deliverables are complete. | Only deliverable is allowing documentation to be updated even after code freeze. On-track. |
Build Performance | Plan for improving performance is defined. | Performance goals for M1 (mostly planning goals) were met. See schedule for details. Build is at 102 minutes. |
Upstream Commits | Have upstream status updated on 90% of patches (so that we can have a status update) | At 85%, which is good enough for alpha. |
Marketing Deliverables | Giveaway plans defined | At least one giveaway plan has been defined and is in the process of being implemented. |
Publication | M1 release is announced |