The Release Criteria for the various Yocto Project 1.1 releases are below.
Yocto Project 1.1
Release Criteria | Milestone 1 Target | Milestone 1 Status |
Functional Completion | All M1 features and BSPs are in the build. | "see https://wiki.yoctoproject.org/wiki/Yocto_1.1_Schedule for status We need to ensure our release process for the milestones is clearly defined. Beth/Jiajun/Julie will discuss. " |
Build and Release (Yocto) | All M1 features can be built with no errors. | Beth is fixing autobuilder config and will rebuild today. She will also kick off Bernard on master-bernard. QA can begin testing afterwards. |
Build and Release (BSPs) | Core and meta-intel BSPs can be built with no errors. | Beth is fixing autobuilder config and will rebuild today. She will also kick off Bernard on master-bernard. QA can begin testing afterwards. |
Open Bugs | All bugs have been dispositioned. High issues have been fixed. | NEW bugs HIGH priority bugs Action Item: Saul will assign some of Richard's NEW bugs to the correct owners. Action Item: Bruce will check with his team about bugs 414 and 609. Action Item: Saul will check with Dexuan about bug 828. 828 hasn't been looked at in a month. Action Item: Julie will send another email about the New bugs, and Saul will send one to the meta-data team. |
Functional Tests | 100% of planned tests are executed and results are logged in bugzilla. | Not done? |
BSP Testing | 100% of planned tests are executed and results are logged in bugzilla. | Router station and PPC blocked [mpc8315e-rdb & routerstationpro] minimal,sato,sato-sdk images boot failed (nightly build 20110423-1) http://bugzilla.pokylinux.org/show_bug.cgi?id=1006 |
Documentation | M1 documentation deliverables are complete. | No documentation deliverables exist for M1. |
Build Performance | Plan for improving performance is defined. | Will wait until Richard returns for details. |
Upstream Commits | Have upstream status updated on 90% of patches (so that we can have a status update) | We will have status in at least 90% of the patches. It may be status = "pending." |
Marketing Deliverables | Giveaway plans defined | Julie, Jefro, Darren, Tracey are working on a giveaway plan. |
Publication | M1 release is announced |