Yocto Project v1.0 Release Criteria: Difference between revisions

From Yocto Project
Jump to navigationJump to search
Line 16: Line 16:
| Yocto 1.0 code builds reliably
| Yocto 1.0 code builds reliably
''M4 (Gold) criteria:  All features in master can be built with no errors.''
''M4 (Gold) criteria:  All features in master can be built with no errors.''
| bgcolor="orange" | There are two major items blocking stable builds:
| bgcolor="orange" | Four issues:
- Docutils is failing - Saul will discuss with Scott G today.
- We had an issue with builder02 running out of disk space, so some of the build copying was done post-build. This did not effect the build and was dealt with manually after cleaning up the partition.
- Zypper is failing <- Richard is working with Qing.
 
We have until Friday to get these fixed.
- There is an issue with how package-index is being run. I will need to sync up with Jessica to verify how this should be incorporated into the build.
 
- The sanity tests on builder02 failed because builder02 was unable to resolve "localhost". This has been corrected and the sanity tests re-run incrementally: http://autobuilder.pokylinux.org:8010/builders/nightly-internal-sanity/builds/3
 
- The tarball generation buildstep is not branch aware. This will be fixed this week.  In the meantime it was run manually.
|-
|-
! scope="row" | Build and Release
! scope="row" | Build and Release
Line 25: Line 29:
| Yocto BSPs build reliably
| Yocto BSPs build reliably
''M4 (Gold) criteria:  BSPs can be build from master with no errors.''
''M4 (Gold) criteria:  BSPs can be build from master with no errors.''
| bgcolor="yellow" | There are currently four errors Beth is working through.
| bgcolor="yellow" |  
- BSPs did not complete successfully. There were some issue in the actual build mostly centering around:
-- Failing to do_kernel_checkout
-- Unpack issues around svn://svn.o-hand.com/repos
 
- Beagleboard failed doing runstrip on uboot during do_populate_sysroot
|-
|-
! scope="row" | Open Bugs
! scope="row" | Open Bugs
| All bugs dispositioned; Show-stoppers fixed
| All bugs dispositioned; Show-stoppers fixed
''M4 (Gold) criteria:  All bugs have been dispositioned.  Bugs targeted for M4 have been fixed.''
''M4 (Gold) criteria:  All bugs have been dispositioned.  Bugs targeted for M4 have been fixed.''
| bgcolor="orange" | 9 bugs not yet dispositioned (in "New" state); Owners: Edwin, Liping, Nitin, Paul, Qing, Saul
| bgcolor="orange" | 76 total open defects targeted for 1.0
Open bugs: 8 major, 69 normal, 6 minor, 5 enhancement
Critical: 0
High: 14
Medium: 53
Low: 7
Undetermined: 2
|-
|-
! scope="row" | Functional Tests
! scope="row" | Functional Tests
| 100% of planned tests executed and all bugs are logged in bugzilla
| 100% of planned tests executed and all bugs are logged in bugzilla
''M4 (Gold) criteria:  All planned tests are executed and results are logged in bugzilla''
''M4 (Gold) criteria:  All planned tests are executed and results are logged in bugzilla''
| bgcolor="#66FF33" | on-track
| bgcolor="yellow" | - zypper-search failed on qemux-x86_64 on poky-image-lsb and poky-image-sato
|-
|-
! scope="row" | BSP Testing
! scope="row" | BSP Testing
Line 58: Line 71:
''M4 (Gold) criteria:  Goal above is reached.''
''M4 (Gold) criteria:  Goal above is reached.''
| bgcolor="yellow" | Team is down to 97-98 minute builds.  Richard will continue the analysis/tweak cycle; however, attention needs to go to other areas as well this week.  File dependencies is one other low-hanging fruit item Richard would like to investigate.
| bgcolor="yellow" | Team is down to 97-98 minute builds.  Richard will continue the analysis/tweak cycle; however, attention needs to go to other areas as well this week.  File dependencies is one other low-hanging fruit item Richard would like to investigate.
real 109m52.400s
user 393m58.840s
sys 59m25.380s
|-
|-
! scope="row" | Marketing requirements complete
! scope="row" | Marketing requirements complete

Revision as of 16:53, 28 February 2011

Yocto v1.0 Release Criteria

Release Criteria
Release Criteria Target Status
Functional Completion All M1, M2, M3 functional features implemented by EO M3

M4 (Gold) Criteria: All features and BSPs are in build.

see Yocto 1.0 Schedule#Stabilization Phase Features and Activities

Richard will send a note regarding the four open features.

Build and Release

(Yocto)

Yocto 1.0 code builds reliably

M4 (Gold) criteria: All features in master can be built with no errors.

Four issues:

- We had an issue with builder02 running out of disk space, so some of the build copying was done post-build. This did not effect the build and was dealt with manually after cleaning up the partition.

- There is an issue with how package-index is being run. I will need to sync up with Jessica to verify how this should be incorporated into the build.

- The sanity tests on builder02 failed because builder02 was unable to resolve "localhost". This has been corrected and the sanity tests re-run incrementally: http://autobuilder.pokylinux.org:8010/builders/nightly-internal-sanity/builds/3

- The tarball generation buildstep is not branch aware. This will be fixed this week. In the meantime it was run manually.

Build and Release

(BSPs)

Yocto BSPs build reliably

M4 (Gold) criteria: BSPs can be build from master with no errors.

- BSPs did not complete successfully. There were some issue in the actual build mostly centering around: -- Failing to do_kernel_checkout -- Unpack issues around svn://svn.o-hand.com/repos

- Beagleboard failed doing runstrip on uboot during do_populate_sysroot

Open Bugs All bugs dispositioned; Show-stoppers fixed

M4 (Gold) criteria: All bugs have been dispositioned. Bugs targeted for M4 have been fixed.

76 total open defects targeted for 1.0

Critical: 0 High: 14 Medium: 53 Low: 7 Undetermined: 2

Functional Tests 100% of planned tests executed and all bugs are logged in bugzilla

M4 (Gold) criteria: All planned tests are executed and results are logged in bugzilla

- zypper-search failed on qemux-x86_64 on poky-image-lsb and poky-image-sato
BSP Testing 100% of planned BSP tests executed

M4 (Gold) criteria: All planned BSP tests are executed

Team hasn't get been able to do a full BSP test pass. Open issues exist with respect to the BSPs (Julie).
Alpha Feedback Alpha feedback included

M4 (Gold) criteria: Alpha begins Feb 11th and completes Feb 23rd

Program completed. Someone just needs to parse final results.
Documentation Release documentation created and published

M4 (Gold) criteria: M4 schedule items completed

Yocto_1.0_Schedule#Documentation_Deliverables
Build Performance Build takes 90 minutes (stretch goal = one hour) to do a complete rebuild of local sources of poky-image-sato on a developer's desktop. (The one we are using is: Intel(R) Core(TM) i7 CPU 940 @ 2.93GHz, 8 siblings, 4 cpu cores, total mem 6118644k, with: MACHINE=qemux86, BB_NUMBER_THREADS = "8", PARALLEL_MAKE = "-j 6", and only rpm packaging.)

M4 (Gold) criteria: Goal above is reached.

Team is down to 97-98 minute builds. Richard will continue the analysis/tweak cycle; however, attention needs to go to other areas as well this week. File dependencies is one other low-hanging fruit item Richard would like to investigate.

real 109m52.400s user 393m58.840s sys 59m25.380s

Marketing requirements complete Engineering requirements to the marketing plan are complete

M4 (Gold) criteria: Yocto demo is prepared for ELC.

Hardware plan defined. Need videos. Need plexiglass boxes. Coding effort underway, but not complete.
Publication Release and documentation are published on yoctoproject.org

M4 (Gold) criteria: Yocto Project 1.0 published and announced

Tunnel Creek BSP Release Criteria

Release Criteria
Release Criteria Target Status
Development progress Features implemented; Code completed Coding completed
Build and Release EMGD and non-EMGD BSPs build reliably Build completed
Open Bugs All bugs dispositioned; Show-stoppers fixed Only minor bugs found (724, 725)
Functional Tests 100% of planned tests executed Tom tested. Jiajun will test Thursday.
Legal Compliance All legal requirements met Account is set up for click-through. Click-through team has info they need.
Documentation Release Notes created and published Scott/Tom are finalizing and things look good.
Performance Performance targets achieved This will be done out of cycle.
Publication Release and documentation are published on yoctoproject.org on-track

Laverne Point Release Criteria

Release Criteria
Release Criteria Target Status
Development Progress Coding complete Coding completed
Build and Release Code builds reliably Release candidate is built.
Open Bugs All bugs dispositioned; Show-stoppers fixed No opens are show-stoppers. Open issues will be ID'd in release notes.
Functional Tests 100% of planned tests executed testing completed
Legal Compliance All legal requirements met tools run; requirements met
Performance Performance targets achieved N/A
Publication Release and documentation are published on yoctoproject.org Complete