Line 78: Line 78:
! scope="row" | Build and Release
! scope="row" | Build and Release
| EMGD and non-EMGD BSPs build reliably
| EMGD and non-EMGD BSPs build reliably
| bgcolor="#66FF33" | Both images are respun.  Beth will package Tues 2/8/2011
| bgcolor="#66FF33" | Both images are respun.  Beth packaged up tarballs and sent link to Tom
|-
|-
! scope="row" | Open Bugs
! scope="row" | Open Bugs
Line 104: Line 104:
| bgcolor="yellow" | on-track
| bgcolor="yellow" | on-track
|}
|}


== Laverne Point Release Criteria ==
== Laverne Point Release Criteria ==

Revision as of 01:06, 9 February 2011

Yocto v1.0 Release Criteria

Release Criteria
Release Criteria Target Status
Functional Completion All M1, M2, M3 functional features implemented by EO M3

Current Criteria: Functional features are ready to go into master.

see Yocto 1.0 Schedule#Stabilization Phase Features and Activities
Build and Release

(Yocto)

Yocto 1.0 code builds reliably

Current criteria: All features in master can be built.

on-track to have stable builds by the end of Master Stabilization phase
Build and Release

(BSPs)

Yocto BSPs build reliably

Current criteria: Plan in place to build/QA BSPs by EO Feb.

Meeting Thursday to determine plan. Next Wednesday, the BSP build server will be off-line for a move, which may impact dates.
Open Bugs All bugs dispositioned; Show-stoppers fixed

Current criteria: All bugs have been dispositioned.

bug count is high; bug triage meetings will hopefully address
Functional Tests 100% of planned tests executed and all bugs are logged in bugzilla

Current criteria: Weekly testing is performed on master and all bugs in bugzilla

testing starts in Feb
BSP Testing 100% of planned BSP tests executed

Current criteria: TBD - pending BSP plan

Alpha Feedback Alpha feedback included

Current criteria: Alpha begins Feb 11th

on-track; need to ensure autobuilder caches the sources (it does) and need to ensure someone can perform a build using autobuilder as the pre-mirror; also need a tag on the build for alpha; Julie will work with Saul and Beth on this.
Documentation Release documentation created and published

Current criteria: M4 schedule items completed

on-track
Build Performance Build performance targets achieved

Current criteria: Performance features are in master

see Yocto 1.0 Schedule; one additional goal could be that the build completes in 90 minutes or less with a single socket desktop system. First, we need to get real build statistics to see if that is realistic to achieve given where we are in the schedule. Julie to ask Jaijun if he has statistics.
Marketing requirements complete Engineering requirements to the marketing plan are complete

Current criteria: Engineering requirements to the marketing plan are known.

need details on requirements
Publication Release and documentation are published on yoctoproject.org

Current criteria: None for this stage

Tunnel Creek BSP Release Criteria

Release Criteria
Release Criteria Target Status
Development progress Features implemented; Code completed Coding completed
Build and Release EMGD and non-EMGD BSPs build reliably Both images are respun. Beth packaged up tarballs and sent link to Tom
Open Bugs All bugs dispositioned; Show-stoppers fixed TBD based on testing of latest build
Functional Tests 100% of planned tests executed Tom will test final tarballs when available. Jaijun will test on Feb 10th. (Need to send note on his return.)
Legal Compliance All legal requirements met Plan in place to create click-through. Getting host set up.
Documentation Release Notes created and published Scott created a draft for Tom's review.
Performance Performance targets achieved This will be done out of cycle.
Publication Release and documentation are published on yoctoproject.org on-track

Laverne Point Release Criteria

Release Criteria
Release Criteria Target Status
Development Progress Coding complete Coding completed
Build and Release Code builds reliably Release candidate is built.
Open Bugs All bugs dispositioned; Show-stoppers fixed No opens are show-stoppers. Open issues will be ID'd in release notes.
Functional Tests 100% of planned tests executed testing completed
Legal Compliance All legal requirements met tools run; requirements met
Performance Performance targets achieved N/A
Publication Release and documentation are published on yoctoproject.org Complete