Yocto 1.1 Schedule: Difference between revisions
From Yocto Project
Jump to navigationJump to search
(added OOB documentation) |
|||
Line 24: | Line 24: | ||
|| Build || Autobuilder maintenance || Bring scripts into configuration or get git repo working for those that can't be brought in. || 1 || Review || Beth || Beth || | || Build || Autobuilder maintenance || Bring scripts into configuration or get git repo working for those that can't be brought in. || 1 || Review || Beth || Beth || | ||
|- | |- | ||
|| Build || License tracking || Get common licenses for all packages. (takes ~3 days) || 1 || | || Build || License tracking || Get common licenses for all packages. (takes ~3 days) || 1 || Accepted || Beth || Beth || | ||
|- | |- | ||
|| Overall || Process Improvement || Host a retrospective to discuss what went well and what can be improved in Yocto 1.0. || 1 || Review || Beth || Beth || | || Overall || Process Improvement || Host a retrospective to discuss what went well and what can be improved in Yocto 1.0. || 1 || Review || Beth || Beth || | ||
Line 30: | Line 30: | ||
|| Project || Release Readiness || Release Readiness Meeting || 1 || Jun-6 || Julie || Julie|| | || Project || Release Readiness || Release Readiness Meeting || 1 || Jun-6 || Julie || Julie|| | ||
|- | |- | ||
|| Point Release || Build/Release/QA || We need a point release to fix bugs targeted for point release. || 1 || | || Point Release || Build/Release/QA || We need a point release to fix bugs targeted for point release. || 1 || Accepted || Beth/Yongkang|| Team|| | ||
|- | |- | ||
|| Performance || Plan for Performance || This is a placeholder to spend time this milestone determining the plan for improving performance. Various P1, P2, P3 tasks will be output as a result of this planning. || 1 || Review || Richard/Dongxiao || Team|| | || Performance || Plan for Performance || This is a placeholder to spend time this milestone determining the plan for improving performance. Various P1, P2, P3 tasks will be output as a result of this planning. || 1 || Review || Richard/Dongxiao || Team|| |
Revision as of 15:49, 29 March 2011
October 2011 (release date: October 6, 2011)
The detailed milestone map for the October 2011 release of Yocto is as below.
pre-M1 (March 14 to April 18 -- Feature List and Schedule Defined April 18)
- Features Submitted to web - by April 1st
- Features prioritized and added to schedule - by April 12th
M1 (Apr 18 to Jun 13 -- Design Complete Apr 25, Dev Complete May 23, Stabilize Complete Jun 6, Release Complete Jun 13)
Group | Feature Name | Description | Priority | Status | Owner | Source | Comments / Bugzilla Links |
Architecture | OE Core | Restructuring, renaming, rebranding | 1 | Review | Richard | Architect | |
1.0 Carryover | multi-lib | multi-lib support for 32-bit & 64-bit and capable of being installed at the same time | 1 | Review | Richard | 1.0 Carryover | |
Meta-Data | OE Comparison | Compare Yocto core set against integration work in OE and other distributions looking for bug fixes, (relevant) feature enhancements, and integration/policy hints. | 1 | Accept | Mark | Meta-data | |
BSPs | Support for AVX as in kernel 2.6.30. - Already in 1.0 | Any toolchain support needed? | 1 | Review | Saul | Jay | |
Misc | User creation at post-install | 1 | Accept | Mark | Architect | ||
Build | Autobuilder maintenance | Bring scripts into configuration or get git repo working for those that can't be brought in. | 1 | Review | Beth | Beth | |
Build | License tracking | Get common licenses for all packages. (takes ~3 days) | 1 | Accepted | Beth | Beth | |
Overall | Process Improvement | Host a retrospective to discuss what went well and what can be improved in Yocto 1.0. | 1 | Review | Beth | Beth | |
Project | Release Readiness | Release Readiness Meeting | 1 | Jun-6 | Julie | Julie | |
Point Release | Build/Release/QA | We need a point release to fix bugs targeted for point release. | 1 | Accepted | Beth/Yongkang | Team | |
Performance | Plan for Performance | This is a placeholder to spend time this milestone determining the plan for improving performance. Various P1, P2, P3 tasks will be output as a result of this planning. | 1 | Review | Richard/Dongxiao | Team | |
Documentation | OOB documentation | Create an out of box guide for giveaway systems built using Yocto by EO May. | 1 | Review | ScottR | Julie |
M2 (May 30 to Jul 25 -- Design Complete Jun 6, Dev Complete Jul 4, Stabilize Complete Jul 18, Release Complete Jul 25)
Group | Feature Name | Description | Priority | Status | Owner | Source | Comments / Bugzilla Links |
1.0 Carryover | Image Creator | finish the Image Creator to add features pushed out from 1.0 | 1 | Accept | Joshua + Jessica | 1.0 Carryover | |
Architecture | Layer Tooling | This includes the architectural work plus implementing the changes | 1 | Review | Richard | Architect | |
Meta-data | Upstream our patches | Placeholder for time for the team to upstream patches | 1 | Review | Saul | Meta-Data Team | |
Meta-data | Error handling in bitbake | add additional error handling to bitbake | 1 | Review | Saul | Architect | |
ADT | Changes for Image Creator | Eclipse changes pending Image Creator | 1 | Review | Jessica | ADT Team | |
BSP | Tutorials | Create tutorials and documentation on how to create a BSP | 1 | Accept | Tom, Scott | Team | |
Kernel | Fast Boot Time | 2 second boot time target | 1 | Accept | Darren | Team | |
Build | Meta-Targets | Part of the challenge of autobuilder is that you have to go into autobuilder, edit script, reconfigure, to change just one build target. This is error prone. What we need is a meta-target where Beth can say she wants to build Poky-image-sato for QEMU x86 and have it just do that. Beth thinks this is done via an override to the web page. (takes ~2 weeks) | 1 | Review | Beth | Beth | |
Build | License History | Build a parser to do license history more gracefully and make sure all recipes are correct. (takes ~2 weeks) | 1 | Review | Beth | Beth | |
Build | Autobuilder Infrastructure | Bring up additional autobuilders and work with sysadmin to configure. | 1 | Review | Beth | Beth | |
Misc | adding eglibc config control | this goes with the package config options | 1.5 | Accept | Mark | Architect | |
Misc | Directory Ownership | 1.5 | Accept | Mark | Architect | a bit concerned this will take longer then expected | |
Project | Release Readiness | Release Readiness Meeting | 1 | Jul-18 | Julie | Julie |
M3 (Jul 11 to Aug 15 -- Design Complete Jul 18, Dev Complete Jul 25, Stabilize Complete Aug 8, Release Complete Aug 15)
Group | Feature Name | Description | Priority | Status | Owner | Source | Comments / Bugzilla Links |
Build | Release Scripts | Create Release Scripts for OCT 2011 release | 1 | Review | Beth | Beth | |
Project | Release Readiness | Release Readiness Meeting | 1 | Aug-8 | Julie | Julie | |
Alpha | Alpha Program | Participants determined - Aug 1; Program - Aug 8-22; Feedback available - Aug 25 | 1 | Accept | Julie | Julie |
M4 (Aug 15 to Oct 6 -- Stabilize Complete Aug 29, Release Complete Oct 3)
Group | Feature Name | Description | Priority | Status | Owner | Source | Comments / Bugzilla Links |
Project | Release Candidate 1 | RC1 generated | 1 | Aug-29 | Beth | Team | |
Project | Release Candidate 2 | RC2 generated | 1 | Sep-5 | Beth | Team | |
Project | Release Candidate 3 | RC3 generated | 1 | Sep-12 | Beth | Team | |
Project | Release Candidate 4 | RC4 generated | 1 | Sep-19 | Beth | Team | |
Project | Release Readiness | Release Readiness Meeting | 1 | Sep-26 | Julie | Julie | |
QA | Holiday | QA team on holiday Oct 1 - 7 | 1 | Oct 1-7 | QA | QA |