Line 7: | Line 7: | ||
! scope="row" | Development Progress | ! scope="row" | Development Progress | ||
| All M1, M2, M3 features implemented by EO M3 | | All M1, M2, M3 features implemented by EO M3 | ||
''Current Criteria: Features are ready to go into master.'' | |||
| bgcolor="yellow" | on-track | | bgcolor="yellow" | on-track | ||
|- | |- | ||
! scope="row" | Build and Release | ! scope="row" | Build and Release | ||
| Yocto 1.0 | (Yocto) | ||
| bgcolor="orange" | have many changes left to merge into master | | Yocto 1.0 code builds reliably | ||
''Current criteria: All features in master can be built.'' | |||
| bgcolor="orange" | have many changes left to merge into master | |||
|- | |||
! scope="row" | Build and Release | |||
(BSPs) | |||
| Yocto BSPs build reliably | |||
''Current criteria: Plan in place to build/QA BSPs by 1.0 release.'' | |||
| bgcolor="orange" | Resourcing constraints. Brainstorming whether the BSPs can be build/tested Feb 27th-March 19th. | |||
|- | |- | ||
! scope="row" | Open Bugs | ! scope="row" | Open Bugs | ||
| All bugs dispositioned; Show-stoppers fixed | | All bugs dispositioned; Show-stoppers fixed | ||
''Current criteria: All bugs have been dispositioned.'' | |||
| bgcolor="orange" | bug count is high; bug triage meetings will hopefully address | | bgcolor="orange" | bug count is high; bug triage meetings will hopefully address | ||
|- | |- | ||
! scope="row" | Functional Tests | ! scope="row" | Functional Tests | ||
| 100% of planned tests executed | | 100% of planned tests executed | ||
''Current criteria: Weekly testing is performed on master'' | |||
| bgcolor="yellow" | testing starts in Feb | | bgcolor="yellow" | testing starts in Feb | ||
|- | |- | ||
! scope="row" | BSP Testing | ! scope="row" | BSP Testing | ||
| 100% of planned BSP tests executed | | 100% of planned BSP tests executed | ||
| bgcolor=" | ''Current criteria: TBD - pending BSP plan'' | ||
| bgcolor="white" | | |||
|- | |- | ||
! scope="row" | Legal Compliance | ! scope="row" | Legal Compliance | ||
| All legal requirements met | | All legal requirements met | ||
''Current criteria: Legal review Feb 22nd'' | |||
| bgcolor="yellow" | in progress | | bgcolor="yellow" | in progress | ||
|- | |- | ||
! scope="row" | Alpha Feedback | ! scope="row" | Alpha Feedback | ||
| Alpha feedback included | | Alpha feedback included | ||
| bgcolor="yellow" | testing starts | ''Current criteria: Alpha begins Feb 11th'' | ||
| bgcolor="yellow" | testing starts Feb 11th | |||
|- | |- | ||
! scope="row" | Documentation | ! scope="row" | Documentation | ||
| Release Notes created and published | | Release Notes created and published | ||
| bgcolor=" | ''Current criteria: None yet'' | ||
| bgcolor="white" | | |||
|- | |- | ||
! scope="row" | Performance | ! scope="row" | Performance | ||
| Performance targets achieved | | Performance targets achieved | ||
| bgcolor="yellow" | TBD | ''Current criteria: Performance enhancement code in master'' | ||
| bgcolor="yellow" | TBD | |||
|- | |- | ||
! scope="row" | Publication | ! scope="row" | Publication | ||
| Release and documentation are published on yoctoproject.org | | Release and documentation are published on yoctoproject.org | ||
| bgcolor=" | ''Current criteria: None for this stage'' | ||
| bgcolor="white" | | |||
|} | |} | ||
Revision as of 21:50, 3 February 2011
Release Criteria | Target | Status |
---|---|---|
Development Progress | All M1, M2, M3 features implemented by EO M3
Current Criteria: Features are ready to go into master. |
on-track |
Build and Release
(Yocto) |
Yocto 1.0 code builds reliably
Current criteria: All features in master can be built. |
have many changes left to merge into master |
Build and Release
(BSPs) |
Yocto BSPs build reliably
Current criteria: Plan in place to build/QA BSPs by 1.0 release. |
Resourcing constraints. Brainstorming whether the BSPs can be build/tested Feb 27th-March 19th. |
Open Bugs | All bugs dispositioned; Show-stoppers fixed
Current criteria: All bugs have been dispositioned. |
bug count is high; bug triage meetings will hopefully address |
Functional Tests | 100% of planned tests executed
Current criteria: Weekly testing is performed on master |
testing starts in Feb |
BSP Testing | 100% of planned BSP tests executed
Current criteria: TBD - pending BSP plan |
|
Legal Compliance | All legal requirements met
Current criteria: Legal review Feb 22nd |
in progress |
Alpha Feedback | Alpha feedback included
Current criteria: Alpha begins Feb 11th |
testing starts Feb 11th |
Documentation | Release Notes created and published
Current criteria: None yet |
|
Performance | Performance targets achieved
Current criteria: Performance enhancement code in master |
TBD |
Publication | Release and documentation are published on yoctoproject.org
Current criteria: None for this stage |
Release Criteria | Target | Status |
---|---|---|
Development progress | Features implemented; Code completed | Coding completed |
Build and Release | EMGD and non-EMGD BSPs build reliably | Both images are built. |
Open Bugs | All bugs dispositioned; Show-stoppers fixed | in progress - removable media issue will be documented as bug and logged in Release Notes |
Functional Tests | 100% of planned tests executed | Tom is testing both now. Jaijun will test on Feb 10th. (Need to send note on his return.) |
Legal Compliance | All legal requirements met | plan in place to create click-through get plan approved |
Documentation | Release Notes created and published | Scott created a draft for Tom's review. |
Performance | Performance targets achieved | This will be done out of cycle. |
Publication | Release and documentation are published on yoctoproject.org | on-track |
Release Criteria | Target | Status |
---|---|---|
Development Progress | Coding complete | Coding completed |
Build and Release | Code builds reliably | Release candidate is built. |
Open Bugs | All bugs dispositioned; Show-stoppers fixed | No opens are show-stoppers. Open issues will be ID'd in release notes. |
Functional Tests | 100% of planned tests executed | testing completed |
Legal Compliance | All legal requirements met | tools run; requirements met |
Performance | Performance targets achieved | N/A |
Publication | Release and documentation are published on yoctoproject.org | on-track |