Yocto Project v1.0 Release Criteria: Difference between revisions

From Yocto Project
Jump to navigationJump to search
(updated with Mar 24, 2011 status)
(added latest on ADT)
Line 14: Line 14:
(Yocto)
(Yocto)
|''M4 (Gold) criteria:  All features in master can be built with no errors.''
|''M4 (Gold) criteria:  All features in master can be built with no errors.''
| bgcolor="yellow" | Builds are green.  IPK repo for ADT needs to be rebuiltScott and Lianhao will do Thursday.
| bgcolor="yellow" | Builds are green.  IPK repo for ADT was rebuild.  Lianhao noticed DISTRO_VERSION was incorrectly setTo fix, we need to rebuild toolchain and ADT repo.
|-
|-
! scope="row" | Build and Release
! scope="row" | Build and Release

Revision as of 13:58, 25 March 2011

Yocto v1.0 Release Criteria

Release Criteria
Release Criteria Target Status
Functional Completion M4 (Gold) Criteria: All M1, M2, M3 features and BSPs are in build. see Yocto 1.0 Schedule#Stabilization Phase Features and Activities

All planned features are in build.

Build and Release

(Yocto)

M4 (Gold) criteria: All features in master can be built with no errors. Builds are green. IPK repo for ADT was rebuild. Lianhao noticed DISTRO_VERSION was incorrectly set. To fix, we need to rebuild toolchain and ADT repo.
Build and Release

(BSPs)

M4 (Gold) criteria: Core and meta-intel BSPs can be built with no errors. Builds are green.
Open Bugs M4 (Gold) criteria: All bugs have been dispositioned. Critical/High bugs targeted for M4 have been fixed. All High priority bugs have been dispositioned. All High priority bugs for 1.0 are fixed.
Functional Tests M4 (Gold) criteria: 100% of planned tests are executed and results are logged in bugzilla QA has completed test pass except for compliance testing.
BSP Testing M4 (Gold) criteria: 100% of planned BSP tests are executed QA has completed test pass except for compliance testing.
Alpha Feedback M4 (Gold) criteria: Alpha runs Feb 11th - Feb 23rd. Feedback is dispositioned. Program completed. Issues have been dispositioned.
Documentation M4 (Gold) criteria: Release documentation created and published Planned documentation deliverables are completed. See Yocto_1.0_Schedule#Documentation_Deliverables
Build Performance M4 (Gold) criteria: Build takes 90 minutes (stretch goal = one hour) to do a complete rebuild of local sources of poky-image-sato on a developer's desktop. (The one we are using is: Intel(R) Core(TM) i7 CPU 940 @ 2.93GHz, 8 siblings, 4 cpu cores, total mem 6118644k, with: MACHINE=qemux86, BB_NUMBER_THREADS = "8", PARALLEL_MAKE = "-j 6", and only rpm packaging.) At 105 minutes. Team decision that this is not a blocker for 1.0.
ADT User Workshop M4 (Gold) criteria: ADT User Workshop is held where developers use ADT tools to demo software, and results are included. Running into problems recruiting people, but not a blocker for 1.0 release.
Upstream Commits M4 (Gold) criteria: No goals for Yocto 1.0 - Yocto 1.1 will include more goals.
Marketing requirements from Engineering complete M4 (Gold) criteria: Yocto demo is prepared for ELC. Top issues:

Need to fix bug 919 so that rygel works and audio/video can be played. (Tom/Josh investigating)
Need to get video to work on at least one piece of hardware. (Tom working on.)
Need to ensure PPC can be used as a Content Store. (Scott G is working on.)

Publication M4 (Gold) criteria: Release and documentation are published on yoctoproject.org and Yocto 1.0 is announced Release process beginning. Julie is pulling together plan.

Tunnel Creek BSP Release Criteria

Release Criteria
Release Criteria Target Status
Development progress Features implemented; Code completed Coding completed
Build and Release EMGD and non-EMGD BSPs build reliably Build completed
Open Bugs All bugs dispositioned; Show-stoppers fixed Only minor bugs found (724, 725)
Functional Tests 100% of planned tests executed 100% testing complete
Legal Compliance All legal requirements met Click-through completed
Documentation Release Notes created and published Done
Performance Performance targets achieved This will be done out of cycle.
Publication Release and documentation are published on yoctoproject.org Done

Laverne Point Release Criteria

Release Criteria
Release Criteria Target Status
Development Progress Coding complete Coding completed
Build and Release Code builds reliably Release candidate is built.
Open Bugs All bugs dispositioned; Show-stoppers fixed No opens are show-stoppers. Open issues will be ID'd in release notes.
Functional Tests 100% of planned tests executed testing completed
Legal Compliance All legal requirements met tools run; requirements met
Performance Performance targets achieved N/A
Publication Release and documentation are published on yoctoproject.org Complete