Yocto Project v1.2 Status

From Yocto Project
Jump to navigationJump to search

Yocto Project 1.2 release Status

Feature/Task Board

Design Design Review Development Patch Review Testing Done
1634 [1], Bruce, 1 1644[2], Bruce, 1 1564[3], Dongxiao, 1
1580[4], Jessica, 1 1008[5], ScottG, 1
1582[6], Joshua, 1
1603[7], Kai, 1
1589[8], Robert, 1
1598[9], Paul, 1
1567[10], Yi, 1

Note: Each column lists "Feature #, Owner, # of weeks in this stage".

Feature/Task Effort Burndown Chart

Feature-burndown12.png

Yocto Project 1.2 Release Criteria

Milestone 1

Release Criteria Milestone 1 Target Milestone 1 Status
Functional Completion All P1 features are completed. See https://wiki.yoctoproject.org/wiki/Yocto_1.2_Schedule for details.
Build and Release (Yocto) All completed features can be built with no errors.
Build and Release (BSPs) Core and meta-intel BSPs can be built with no errors.
Open Bugs All bugs have been dispositioned. High issues have been fixed. [11] - new bugs for 1.2.
HIGH priority bugs - high bugs for 1.2
See trend chart at https://wiki.yoctoproject.org/wiki/Yocto_Bug_Trend.
Functional Tests 100% of planned tests are executed and results are logged in bugzilla. https://wiki.yoctoproject.org/wiki/Yocto_1.2_Milestone_Test_Report
Distros Tested Fedora, Ubuntu, Opensuse Fedora 15, Ubuntu 11.04, Opensuse 11.4
BSP Testing 100% of planned tests are executed and results are logged in bugzilla. https://wiki.yoctoproject.org/wiki/Yocto_1.2_Milestone_Test_Report
Documentation All scheduled docs are complete
Build Performance None N/A
Upstream Commits Have upstream status updated on 90% of patches (so that we can have a status update) Complete
Marketing Deliverables None N/A
Publication Yocto 1.2, Milestone 1 release is announced