Yocto Project Weekly Status Aug. 11, 2020

Current Dev Position: YP 3.2 M3
Next Deadline: YP 3.2 M3 build date 2020/8/31

Next Team Meetings:

Key Status/Updates:

  • YP 3.2 M2 is out of QA and going through release approval
  • We’re now in M3 which is the last milestone for new feature development for this release
  • YP 3.0.4 is due to be built this week and will be the last point release for zeus as we migrate over to our new LTS policy and cadence.
  • A number of new intermittent autobuilder failures were seen this week and logged in bugzilla including one showing signs of another bitbake lockfile race issue.

You can see the rest of the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT Help with any of these would be much appreciated, unfortunately it is proving hard to find anyone interested in helping figure these out and they significantly hamper our testing.

YP 3.2 Milestone Dates:

  • YP 3.2 M2 should release soon.
  • YP 3.2 M3 build date 2020/8/31
  • YP 3.2 M3 Release date 2020/9/11
  • YP 3.2 M4 build date 2020/10/5
  • YP 3.2 M4 Release date 2020/10/30

Planned upcoming dot releases:

  • YP 3.0.4 build date 2020/8/10
  • YP 3.0.4 release date 2020/8/21
  • YP 3.1.3 build date 2020/9/14
  • YP 3.1.3 release date 2020/9/25

Tracking Metrics:

The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at: