Web Hob design project with T&T: Difference between revisions

From Yocto Project
Jump to navigationJump to search
Line 10: Line 10:
* [[File:User_Test_1_Findings-INT-002.pdf‎|User Test Findings, Round 1]] - Summary of feedback gathered on the Stage 1 designs  
* [[File:User_Test_1_Findings-INT-002.pdf‎|User Test Findings, Round 1]] - Summary of feedback gathered on the Stage 1 designs  
* [[File:Wireframes-Stage_1-INT-002-0.10.pdf|Wireframes 0.10]] — Final Stage 1 Wireframes (bright blue links, buttons, etc. are clickable)
* [[File:Wireframes-Stage_1-INT-002-0.10.pdf|Wireframes 0.10]] — Final Stage 1 Wireframes (bright blue links, buttons, etc. are clickable)
* [[File:https://wiki.yoctoproject.org/wiki/File:Web_Hob_content_structure.pdf|Web Hob content structure]] - An outline of the structure of the Web Hob application
<br>
<br>
[https://wiki.yoctoproject.org/wiki/Web_UI#Old_Files older files]
[https://wiki.yoctoproject.org/wiki/Web_UI#Old_Files older files]

Revision as of 15:05, 8 February 2013

This page contains information on the Web Hob project to develop a web-based UI for the Yocto project.

Mailing List: https://lists.yoctoproject.org/listinfo/webhob


Design

Latest Files


older files


Stage II & III

Scenarios Covered

  • Create Build 
    • Set up Project 
    • Choose Hardware
    • Set Preferences 
    • Specify Layer(s)
    • Specify base image and package(s)
    • Run Build
  • Install Web Hob Server
    • Configure team servers 
    • Select team options and configure
  • Error Messaging 
    • View error logs
  • Refine scenarios from Stage I


Schedule

  • 4 Feb 2013 — Workshop
  • 8 Feb — 1st review
  • 12–14 Feb — User testing
  • 15 Feb — User testing review
  • 20 Feb — 2nd review
  • 22 Feb — Final review




Stage I

Scenarios Covered

  • Show Build Metrics (minimal)
    • Identify image (minimal)
    • Define scope of analysis (minimal)
    • Run analysis of image (minimal)
    • View analysis overview (minimal)
  • Finding/Viewing Builds (minimal)
    • View list of projects/builds (minimal)
  • Install Single-User Web Hob (minimal)
    • Check prerequisites (minimal)
    • Download/git clone Web Hob (minimal)
    • Install single-user option (minimal)


Schedule

  • 11 Jan 2013 — Kickoff
  • 14 Jan — Workshop
  • 18 Jan — 1st review
  • 22–24 Jan — User testing
  • 25 Jan — User testing review
  • 30 Jan — 2nd review
  • 1 Feb — Final review


Old Files




Previous Versions